The CCMA is currently undertaking pathway reconstruction works along the Barwon River through Geelong. This is targeting priority sections of the shared-use trail that are in poor condition and are in need of improvement after recent flooding events. Once the work is finished it will provide a great improvement to general access throughout the river reserves.
Over the next two months of January and February 2023 there will be temporary closures of sections of the pathway with no access permitted for short periods of time. It is advised that the public plan ahead and find another route for this period if required.
There are four separate areas that will be closed at various dates that are detailed below:
Area 1 – Riversdale Road Entrance
Closure from January 12th to January 25th 2023
Area 2 – Pakington Street Entrance
Closure from January 23rd to February 13th 2023
Area 3 – Shannon Avenue Underpass
Closure from January 30th to February 13th 2023
Area 4 – Belmont Common
Closure from February 7th to February 28th 2023
64 Dennis Street, Colac VIC 3250
PO Box 159, Colac, VIC 3250
Hours: 8:30am – 5pm, Monday to Friday
T: 1800 002 262
E: info@ccma.vic.gov.au
BARWON WATER OFFICES
Hours: 8:30am – 5pm, Monday to Friday
All mail must be sent via our Colac office
PO Box 159, Colac, VIC 3250
T: 1800 002 262
E: info@ccma.vic.gov.au